Quarterly Cityline Community Meeting

Construction for Cityline Sunnyvale is progressing well. Join us for our Quarterly Meeting on July 8th for progress updates and information…

Construction for Cityline Sunnyvale is progressing well. Join us for our Quarterly Meeting on July 8th for progress updates and information.

July 8th, 2024

6pm

Hunter Properties, Inc. - Community Benefits Rooms
10121 Miller Ave. Suite 200
Cupertino, CA 95014


April 26, 2024

A summary of street/lane closures and extended work hours approved by the City of Sunnyvale to accommodate construction from May 1, 2024 through...

A summary of street/lane closures and extended work hours approved by the City of Sunnyvale to accommodate construction from May 1, 2024 through June 30, 2024 is provided. These dates are subject to change, view schedule HERE.

Construction Hours and Road Closures


APRIL 9, 2024

PG&E Electrical Outage Notice

We have recently been informed by PG&E that they have scheduled an electrical outage affecting properties on and adjacent to Washington, between Taaffe and Frances, to facilitate...

We have recently been informed by PG&E that they have scheduled an electrical outage affecting properties on and adjacent to Washington, between Taaffe and Frances, to facilitate the energization of our construction project. It is possible that your address may be affected by this outage on April 15, 2024, beginning at approximately 6:00 am. If your property is indeed affected, you should have already received a notification from PG&E.


The Cityline Block 3 North commercial office project located at 250 Washington Ave (West Building) is erecting its final tier of structural steel at levels 7 and Roof and is placing concrete fill on the metal decks at levels 2 & 3...

The Cityline Block 3 North commercial office project located at 250 Washington Ave (West Building) is erecting its final tier of structural steel at levels 7 and Roof and is placing concrete fill on the metal decks at levels 2 & 3.

The Cityline Block 3 North commercial office project located at 200 Washington Ave (East Building) has its steel erected through level 4.

The Cityline Block 3 South residential project, called “The Martin”, located at 240 S. Taaffe St is a poured in place structural concrete project with the West Building at Level 11 and the East Building at level 8.

Read the full update HERE

Cityline Block 3 Update



MARCH 24, 2022

The excavation includes the removal of approximately 250,000 cubic yards of dirt to support the construction of two levels of below grade garages across nearly the entire footprint of the site...

The excavation includes the removal of approximately 250,000 cubic yards of dirt to support the construction of two levels of below grade garages across nearly the entire footprint of the site.

As of March 24th, approximately 12-15’ below ground surface worth of dirt has been removed from the site, and now we’re working on installing tiebacks around the perimeter of the site to reinforce the structural integrity of the lagging and soldier beams before moving forward with the remaining excavation around the site.

The remaining excavation activities should take another few months, and then we will begin erecting four tower cranes onsite and pouring our mat foundations. The mat pours and crane erections have been diligently coordinated with the City of Sunnyvale, Downtown Association and other stakeholders to minimize the interruption to the downtown. We ask for your continued patience as we move forward with these projects!

Mass excavation activities at Block 3 of Cityline have begun!


Cityline Sunnyvale is now under construction!

Construction for Cityline at Downtown Sunnyvale is underway! The construction area downtown is bounded by Washington, Murphy, McKinley and Taaffe...

Construction for Cityline at Downtown Sunnyvale is underway! The construction area downtown is bounded by Washington, Murphy, McKinley and Taaffe.

This phase of work consists of two 12-story residential towers and two seven-story office buildings. CLICK HERE for a summary of street and lane closures to pour concrete and install cranes. These dates are subject to change, and will be updated real time on our website.

For information on other downtown businesses and events, visit: SunnyvaleDowntown.com.


JULY 21, 2021

Macy’s has been demolished!

We’re excited that this monumental milestone for downtown is completed. We will continue to off haul material throughout the month of July and then finalize by removing the slab the first couple of weeks of August...

We’re excited that this monumental milestone for downtown is completed. We will continue to off haul material throughout the month of July and then finalize by removing the slab the first couple of weeks of August.

When all of that work is done we’ll be pulling back our fence to fully open the surface parking lot that’s nearest to the redwood trees. Lastly, construction at the “Flats West” is nearing completion, and leasing has begun! If you’re interested in leasing please go to the residential section of this website.

The Cityline Block 3 North Office buildings located at 250 Washington Ave (West Building) and 200 Washington Ave (East Building) has topped out steel erection...

The Cityline Block 3 North Office buildings located at 250 Washington Ave (West Building) and 200 Washington Ave (East Building) has topped out steel erection. The topping out ceremony was held on May 9th to celebrate this milestone. The façade installation has started at 250 Washington Ave and over the next few months, the terracotta panels and the glass will be installed. Other ongoing activities include the installation of the mechanical, electrical and plumbing systems.

The Martin (AKA Block 3 South residential buildings) located at 240 S. Taaffe St has topped out on both the East and West Buildings as of June 14th. The installation of the exterior façade has commenced on the West building with the GFRC panels and will be followed by glass installation. The façade for the East tower will start subsequently in early July.

Read the full update HERE

Cityline Block 3 Update