Cityline Downtown Sunnyvale Construction

Construction

NEWS

CITYLINE QUARTERLY
CONSTRUCTION UPDATE

January 9, 2023 6:00pm

Cityline Marketing and Community Benefits Room
241 S Taaffe Street, Suite 160
Sunnyvale, CA 94086


CITYLINE SUNNYVALE IS NOW UNDER CONSTRUCTION!

August 1, 2022

Construction for Cityline at Downtown Sunnyvale is underway! The construction area downtown is bounded by Washington, Murphy, McKinley and Taaffe.

This phase of work consists of two 12-story residential towers and two seven-story office buildings. CLICK HERE for a summary of street and lane closures to pour concrete and install cranes. These dates are subject to change, and will be updated real time on our website.

For information on other downtown businesses and events, visit:
SunnyvaleDowntown.com.


Mass excavation activities at Block 3 of CityLine has begun!

March 24, 2022

The excavation includes the removal of approximately 250,000 cubic yards of dirt to support the construction of two levels of below grade garages across nearly the entire footprint of the site. As of March 24th, approximately 12-15’ below ground surface worth of dirt has been removed from the site, and now we’re working on installing tiebacks around the perimeter of the site to reinforce the structural integrity of the lagging and soldier beams before moving forward with the remaining excavation around the site. The remaining excavation activities should take another few months, and then we will begin erecting four tower cranes onsite and pouring our mat foundations. The mat pours and crane erections have been diligently coordinated with the City of Sunnyvale, Downtown Association and other stakeholders to minimize the interruption to the downtown. We ask for your continued patience as we move forward with these projects!


MACY'S HAS BEEN DEMOLISHED!

July 21, 2021

We’re excited that this monumental milestone for downtown is completed. We will continue to off haul material throughout the month of July and then finalize by removing the slab the first couple of weeks of August. When all of that work is done we’ll be pulling back our fence to fully open the surface parking lot that’s nearest to the redwood trees. Lastly, construction at the “Flats West” is nearing completion, and leasing has begun! If you’re interested in leasing please go to the residential section of this website.


CITYLINE BUSINESS AND RESIDENT UPDATE

Next Meeting Date TBD

Sign Up To Learn More